Pharmaceutical Company in Manchester

Design & Build of Walk-In Chillstore with an operating range of 2°C to 8°C

Location

Manchester

Date

December 2023

Value Range

£40k- £50K

Product Category

Coldrooms

See more case studies

Repairs to Laboratory Air Conditioning System

Deep Clean of Wall Mounted Air Conditioning System

Read More

Pharmaceutical Walk-In Chillstore

Design, supply & installation of Walk In Pharmaceutical Chillstore with an operating range of 2°C to 8°C.

Read More

Deep Clean of a Wall Mounted Air Conditioning System

Deep Clean of Wall Mounted Air Conditioning System

Read More

Large Refrigeration & Air Conditioning Project for Pharmaceutical Manufacturer

Design, supply & installation of multiple Walk In Pharmaceutical Chillstores, each with an operating range of 2°C to 8°C.

Read More

ICE maintenance contract extends warranty on new equipment for up to 10 years

ICE Ltd the experts in Refrigeration & Air Conditioning, provide a case study of how a maintenance contract extends warranty of new equipment for up to 10 years.

Read More

Design & Build of Walk-In Chillstore

Design, supply & installation of Walk In Pharmaceutical Chillstore with an operating range of 2°C to 8°C.

Read More

A pharmaceutical company responsible for purchasing and importing medicines from other EU countries required a new Walk-In Chillstore for the packaging of pharmaceutical products.

 

Our client operates to the strict requirements laid down by Good Manufacturing and Distribution Practice (GMDP) and the Home Office Requirements for Controlled Drugs.

Scope of work

Our scope of works was to supply and build a new Walk-In Chillstore within first floor area of the site. Operating with a set point of 5°C, the new chillstore required a minimum and maximum range of between 2°C and 8°C.

All the old work areas were to be demolished and removed to create a clear space.

There was a requirement for the new refrigeration systems to provide a fully flexible run and standby operation and to maintain the conditions 24 hours per day, 365 days per year.

Lighting and electrical mains were also required to be included within the project.

How ICE helped

A new walk-in chillstore was built to the following spec:

Enclosure: – 5.7m x 4.5m x 3.0m (high)

Wall panels: – 100mm thick PIR core insulated panels

Ceiling panels: – 100mm thick PIR core insulated panels

 

All panels were finished in White FOODSAFE P.V.C coated galvanized steel to all seen areas.

The floor was manufactured from Polyurethane foam injected modular floor, reinforced with 12mm thick exterior grade plywood foamed in place to upper surface. This was then overlaid with a further layer of 15mm thick phenolic coated plywood complete with slip resistant covering with overlapping joints.

The entrance to this area was via a 1.5m x 2.1m manual sliding door on a Fermod 2150 series track with handles inside and out.

To ensure the critical temperature parameters are maintained, the door was fitted with a door switch that would alarm locally after a pre set period of time of around 30 seconds to prevent the doors being left open.

To serve the walk-in cold room, we have installed two independent, direct expansion refrigeration systems, utilising fully housed condensing units and ceiling mounted evaporator coolers.

Each installed system would be capable of 5.05kw of refrigeration duty, providing a total duty of 10.10kw under the conditions specified. The two systems run together continuously, with each independently capable of maintaining the desired room temperature in the event of a failure to one of the systems or whilst the other is defrosting.

The condensing units installed are Danfoss Optyma Plus packaged units, matched to ceiling mounted coolers manufactured by Kelvion.

The systems are controlled by a bespoke control panel installed internally on the outside of the chillstore. This would indicate refrigeration system activity/status and also indicate any fault signals received.

Electrical mains requirements to the room and energy efficient LED lighting were installed by our electrical contractors E&A Electrical Ltd.

This project was run by our Head of Projects Lee Hopkins and installed by our in-house installation team lead by our onsite supervisor Daniel Bush.

The project was handed over to the client in December 2023 along with as built drawings, commissioning reports and O&M manuals.

 

Results

All the cold room systems were installed to the highest of standards and are performing well.

Since commissioning the cold room, we have received the following feedback from the client:

“I want to extend a special thank you to Lee Hopkins – your communication between us the client and the other contractors has been nothing but perfect! Any issue we have come across has been rectified either the next day, or the day after. The quality of work, as always, is of a very high standard and the working relationship we all have has made it fun to come into work and complete the project with a smile on our face. Thank you very much. “

We are ready to help with your air conditioning, refrigeration and ventilation enquiries.

If you have an enquiry, please complete the contact form and our team will be in touch. We look forward to hearing from you and look forward to building a winning partnership

Get in touch today!

    By sending this message, you agree to the Terms of use and Privacy Policy.

    This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.